Skip to main content

Commercial Pilot Licence (CPAER) – Canada · Question

A company produced 1,000 units, but standard direct materials were budgeted for 950 units. If the actual cost was $10,500 for 1,050 kg of material at $10/kg, and the standard allows 1 kg per unit at $9.50/kg, what is the direct materials price variance?

The direct materials price variance is calculated as (Actual Price - Standard Price) × Actual Quantity. So, ($10/kg - $9.50/kg) × 1,050 kg = $0.50/kg × 1,050 kg

Start free practice for Commercial Pilot Licence (CPAER) – Canada

150 questions · no signup required · 40 free questions per day

Start Practice →

Question: A company produced 1,000 units, but standard direct materials were budgeted for 950 units. If the actual cost was $10,500 for 1,050 kg of material at $10/kg, and the standard allows 1 kg per unit at $9.50/kg, what is the direct materials price variance?

Answer options:

  • $525 unfavourable
  • $525 favourable ✅ $1,050 unfavourable
  • $1,050 favourable

Correct answer: $1,050 unfavourable

Explanation: The direct materials price variance is calculated as (Actual Price - Standard Price) × Actual Quantity. So, ($10/kg - $9.50/kg) × 1,050 kg = $0.50/kg × 1,050 kg = $525 unfavourable.

Start free practice for Commercial Pilot Licence (CPAER) – Canada

150 questions · no signup required · 40 free questions per day

Start Practice →

More about Commercial Pilot Licence (CPAER) – Canada

Related Questions

More for Commercial Pilot Licence (CPAER) – Canada candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Commercial Pilot Licence (CPAER) – Canada Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.