Skip to main content

Excavator Operator Certification Exam Prep · Question

A 600 mm diameter concrete pipe section, 3.0 metres in length, needs to be lifted and placed into a trench. Assuming the density of concrete is approximately 2400 kg/m³, what is the approximate weight of this pipe section, requiring appropriate lifting capacity?

First, calculate the volume: V = \pi * r^2 * L = \pi * (0.3 m)^2 * 3.0 m \approx 0.848 m³. Then, Weight = Volume * Density = 0.848 m³ * 2400 kg/m³ = 2035 kg, wh

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

Question: A 600 mm diameter concrete pipe section, 3.0 metres in length, needs to be lifted and placed into a trench. Assuming the density of concrete is approximately 2400 kg/m³, what is the approximate weight of this pipe section, requiring appropriate lifting capacity?

Answer options:

  • Approximately 1.5 tonnes ✅ Approximately 2.0 tonnes
  • Approximately 0.8 tonnes
  • Approximately 3.5 tonnes

Correct answer: Approximately 2.0 tonnes

Explanation: First, calculate the volume: V = \pi * r^2 * L = \pi * (0.3 m)^2 * 3.0 m \approx 0.848 m³. Then, Weight = Volume * Density = 0.848 m³ * 2400 kg/m³ = 2035 kg, which is approximately 2.0 tonnes. This calculation is crucial for ensuring the excavator's lifting capacity is not exceeded, preventing structural failure or tip-overs.

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

More about Excavator Operator Certification Exam Prep

Related Questions

More for Excavator Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Excavator Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.