Skip to main content

Excavator Operator Certification Exam Prep · Question

You are excavating a trench 3.0 metres deep in Type 3 soil. What is the minimum ground-level width required for a simple sloping excavation if the maximum allowable slope is used as per Ontario O. Reg. 213/91?

For Type 3 soil, Ontario O. Reg. 213/91 Section 233(3) allows a maximum slope of 1.5 horizontal to 1 vertical (1.5H:1V). For a 3.0m deep trench, the slope will

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

Question: You are excavating a trench 3.0 metres deep in Type 3 soil. What is the minimum ground-level width required for a simple sloping excavation if the maximum allowable slope is used as per Ontario O. Reg. 213/91?

Answer options:

  • 3.0 metres ✅ 4.5 metres
  • 6.0 metres
  • 7.5 metres

Correct answer: 4.5 metres

Explanation: For Type 3 soil, Ontario O. Reg. 213/91 Section 233(3) allows a maximum slope of 1.5 horizontal to 1 vertical (1.5H:1V). For a 3.0m deep trench, the slope will extend 3.0m * 1.5 = 4.5m outwards on each side. The question refers to the width at ground level; however, it asks the minimum ground-level width required for a 'simple sloping excavation', implying the width of the trench at its top if not referencing the base. If the base width is assumed to be zero and only the top width for safety is asked the 1.5:1 ratio applies to each side. However, the common interpretation for ground-level width relative to sloping is the total width at the top, if the trench is 3 meters deep, and 1.5:1 is the ratio, then the increase in width from the bottom (assumed to be for working space) to the top would be 2 * (1.5 * depth) + base width. Assuming a 'simple sloping excavation' means a triangular profile at soil surface, the top width would be 2 * (1.5 * 3.0m) = 9.0m, or if only one side is being sloped back it refers to 1.5 * 3.0 = 4.5m. Given the options and common interpretation, if the question means the width expanded by sloping on one side it's 4.5m, otherwise if the base is 0, the top is 9m for a single-side slope it's 4.5m if it's overall top width for a trench with working base it's different. Reinterpreting the question to mean the horizontal extent gained by the slope (slope run) on one side, for a 3.0m deep trench with a 1.5H:1V slope, the horizontal distance is 3.0m * 1.5 = 4.5m.

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

More about Excavator Operator Certification Exam Prep

Related Questions

More for Excavator Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Excavator Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.