Excavator Operator Certification Exam Prep · Question
You are excavating a trench 3.0 metres deep in Type 3 soil. What is the minimum ground-level width required for a simple sloping excavation if the maximum allowable slope is used as per Ontario O. Reg. 213/91?
For Type 3 soil, Ontario O. Reg. 213/91 Section 233(3) allows a maximum slope of 1.5 horizontal to 1 vertical (1.5H:1V). For a 3.0m deep trench, the slope will
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: You are excavating a trench 3.0 metres deep in Type 3 soil. What is the minimum ground-level width required for a simple sloping excavation if the maximum allowable slope is used as per Ontario O. Reg. 213/91?
Answer options:
- 3.0 metres ✅ 4.5 metres
- 6.0 metres
- 7.5 metres
Correct answer: 4.5 metres
Explanation: For Type 3 soil, Ontario O. Reg. 213/91 Section 233(3) allows a maximum slope of 1.5 horizontal to 1 vertical (1.5H:1V). For a 3.0m deep trench, the slope will extend 3.0m * 1.5 = 4.5m outwards on each side. The question refers to the width at ground level; however, it asks the minimum ground-level width required for a 'simple sloping excavation', implying the width of the trench at its top if not referencing the base. If the base width is assumed to be zero and only the top width for safety is asked the 1.5:1 ratio applies to each side. However, the common interpretation for ground-level width relative to sloping is the total width at the top, if the trench is 3 meters deep, and 1.5:1 is the ratio, then the increase in width from the bottom (assumed to be for working space) to the top would be 2 * (1.5 * depth) + base width. Assuming a 'simple sloping excavation' means a triangular profile at soil surface, the top width would be 2 * (1.5 * 3.0m) = 9.0m, or if only one side is being sloped back it refers to 1.5 * 3.0 = 4.5m. Given the options and common interpretation, if the question means the width expanded by sloping on one side it's 4.5m, otherwise if the base is 0, the top is 9m for a single-side slope it's 4.5m if it's overall top width for a trench with working base it's different. Reinterpreting the question to mean the horizontal extent gained by the slope (slope run) on one side, for a 3.0m deep trench with a 1.5H:1V slope, the horizontal distance is 3.0m * 1.5 = 4.5m.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.