Skip to main content

Heavy Equipment Operator Certification Exam Prep · Question

A project requires moving 8,000 m³ of material. The scraper fleet consists of two units, each with an average hourly production of 120 m³ per hour (accounting for efficiency and cycle time). How many 10-hour shifts will it take to complete the project using both scrapers?

Combined hourly production for two scrapers = 2 units * 120 m³/hour/unit = 240 m³/hour. Total hours needed to move 8,000 m³ = 8,000 m³ / 240 m³/hour = 33.33 hou

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

Question: A project requires moving 8,000 m³ of material. The scraper fleet consists of two units, each with an average hourly production of 120 m³ per hour (accounting for efficiency and cycle time). How many 10-hour shifts will it take to complete the project using both scrapers?

Answer options:

  • 3 shifts
  • 4 shifts
  • 5 shifts ✅ 6 shifts

Correct answer: 6 shifts

Explanation: Combined hourly production for two scrapers = 2 units * 120 m³/hour/unit = 240 m³/hour. Total hours needed to move 8,000 m³ = 8,000 m³ / 240 m³/hour = 33.33 hours. Number of 10-hour shifts = 33.33 hours / 10 hours/shift = 3.33 shifts. Since shifts must be whole, it will take 4 shifts. Oops again. (8000 m³ / 240 m³/hr) = 33.33 hours. 33.33 hours / 10 hours/shift = 3.33 shifts. Since you cannot do a fraction of a shift, it would be 4 shifts. Let me check the provided correct index for this. The correct index is 3 (6 shifts). Where is the discrepancy? Let's re-calculate: 8000 m³ / 120 m³/hr/unit = 66.67 machine hours per unit. For two units working simultaneously, the project hours are 66.67 hours / 2 units = 33.33 hours. So 33.33 hours / 10 hours/shift = 3.33 shifts. Answering 6 shifts would imply something went wrong with calculation. Let me assume a different interpretation of the question. Maybe 120m3/hr is per scraper, and it is independent. No. 'Each with an average hourly production of 120 m³ per hour'. So 2 * 120 = 240 m3/hr. If the answer is 6 shifts, this implies roughly 60 hours total. If 60 hours total, then 60 hrs * 240 m3/hr = 14400 m3, which is more than what is needed... Let's re-examine if the problem is indeed a numerical one. If 8000 m³ is needed, and each scraper does 120 m³/hr, then two scrapers do 240 m³/hr. 8000 / 240 = 33.33 hours. If each shift is 10 hours, then 33.33 / 10 = 3.33 shifts, round up to 4 shifts. There must be an error in the given 'correct_index' for this question. It should be 4 shifts (index 1). I will proceed using the correct calculation: 4 shifts.

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

More about Heavy Equipment Operator Certification Exam Prep

Related Questions

More for Heavy Equipment Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Heavy Equipment Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.