Heavy Equipment Operator Certification Exam Prep · Question
A project requires moving 8,000 m³ of material. The scraper fleet consists of two units, each with an average hourly production of 120 m³ per hour (accounting for efficiency and cycle time). How many 10-hour shifts will it take to complete the project using both scrapers?
Combined hourly production for two scrapers = 2 units * 120 m³/hour/unit = 240 m³/hour. Total hours needed to move 8,000 m³ = 8,000 m³ / 240 m³/hour = 33.33 hou
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
Question: A project requires moving 8,000 m³ of material. The scraper fleet consists of two units, each with an average hourly production of 120 m³ per hour (accounting for efficiency and cycle time). How many 10-hour shifts will it take to complete the project using both scrapers?
Answer options:
- 3 shifts
- 4 shifts
- 5 shifts ✅ 6 shifts
Correct answer: 6 shifts
Explanation: Combined hourly production for two scrapers = 2 units * 120 m³/hour/unit = 240 m³/hour. Total hours needed to move 8,000 m³ = 8,000 m³ / 240 m³/hour = 33.33 hours. Number of 10-hour shifts = 33.33 hours / 10 hours/shift = 3.33 shifts. Since shifts must be whole, it will take 4 shifts. Oops again. (8000 m³ / 240 m³/hr) = 33.33 hours. 33.33 hours / 10 hours/shift = 3.33 shifts. Since you cannot do a fraction of a shift, it would be 4 shifts. Let me check the provided correct index for this. The correct index is 3 (6 shifts). Where is the discrepancy? Let's re-calculate: 8000 m³ / 120 m³/hr/unit = 66.67 machine hours per unit. For two units working simultaneously, the project hours are 66.67 hours / 2 units = 33.33 hours. So 33.33 hours / 10 hours/shift = 3.33 shifts. Answering 6 shifts would imply something went wrong with calculation. Let me assume a different interpretation of the question. Maybe 120m3/hr is per scraper, and it is independent. No. 'Each with an average hourly production of 120 m³ per hour'. So 2 * 120 = 240 m3/hr. If the answer is 6 shifts, this implies roughly 60 hours total. If 60 hours total, then 60 hrs * 240 m3/hr = 14400 m3, which is more than what is needed... Let's re-examine if the problem is indeed a numerical one. If 8000 m³ is needed, and each scraper does 120 m³/hr, then two scrapers do 240 m³/hr. 8000 / 240 = 33.33 hours. If each shift is 10 hours, then 33.33 / 10 = 3.33 shifts, round up to 4 shifts. There must be an error in the given 'correct_index' for this question. It should be 4 shifts (index 1). I will proceed using the correct calculation: 4 shifts.
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
More about Heavy Equipment Operator Certification Exam Prep
Related Questions
More for Heavy Equipment Operator Certification Exam Prep candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Heavy Equipment Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.