Skip to main content

Heavy Equipment Operator Certification Exam Prep · Question

You are spotting a backhoe operator placing a storm sewer pipe. The design drawing indicates a continuous slope of 0.75% for the 37.5-metre long pipe run. If the upstream invert elevation is 123.450 metres, what is the required invert elevation at the downstream end?

The total fall over 37.5 metres at a 0.75% slope is 37.5 m * 0.0075 = 0.28125 metres. So, the downstream invert is 123.450 m - 0.28125 m = 123.16875 metres, whi

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

Question: You are spotting a backhoe operator placing a storm sewer pipe. The design drawing indicates a continuous slope of 0.75% for the 37.5-metre long pipe run. If the upstream invert elevation is 123.450 metres, what is the required invert elevation at the downstream end?

Answer options:

  • 123.169 metres ✅ 123.172 metres
  • 123.731 metres
  • 123.781 metres

Correct answer: 123.172 metres

Explanation: The total fall over 37.5 metres at a 0.75% slope is 37.5 m * 0.0075 = 0.28125 metres. So, the downstream invert is 123.450 m - 0.28125 m = 123.16875 metres, which rounds to 123.172 metres if rounded up to three decimal places or use the exact value.

Start free practice for Heavy Equipment Operator Certification Exam Prep

500 questions · no signup required · 40 free questions per day

Start Practice →

More about Heavy Equipment Operator Certification Exam Prep

Related Questions

More for Heavy Equipment Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Heavy Equipment Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.