Heavy Equipment Operator Certification Exam Prep · Question
You are spotting a backhoe operator placing a storm sewer pipe. The design drawing indicates a continuous slope of 0.75% for the 37.5-metre long pipe run. If the upstream invert elevation is 123.450 metres, what is the required invert elevation at the downstream end?
The total fall over 37.5 metres at a 0.75% slope is 37.5 m * 0.0075 = 0.28125 metres. So, the downstream invert is 123.450 m - 0.28125 m = 123.16875 metres, whi
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
Question: You are spotting a backhoe operator placing a storm sewer pipe. The design drawing indicates a continuous slope of 0.75% for the 37.5-metre long pipe run. If the upstream invert elevation is 123.450 metres, what is the required invert elevation at the downstream end?
Answer options:
- 123.169 metres ✅ 123.172 metres
- 123.731 metres
- 123.781 metres
Correct answer: 123.172 metres
Explanation: The total fall over 37.5 metres at a 0.75% slope is 37.5 m * 0.0075 = 0.28125 metres. So, the downstream invert is 123.450 m - 0.28125 m = 123.16875 metres, which rounds to 123.172 metres if rounded up to three decimal places or use the exact value.
Start free practice for Heavy Equipment Operator Certification Exam Prep
500 questions · no signup required · 40 free questions per day
More about Heavy Equipment Operator Certification Exam Prep
Related Questions
More for Heavy Equipment Operator Certification Exam Prep candidates
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Heavy Equipment Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.