Skip to main content

PMP (Project Management Professional) · Question

A project manager is calculating the estimated cost at completion (EAC) using the formula EAC = AC + ETC. Which scenario most likely applies?

This formula assumes that the actual cost incurred to date (AC) will be supplemented by the Estimate To Complete (ETC) based on project performance.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

Question: A project manager is calculating the estimated cost at completion (EAC) using the formula EAC = AC + ETC. Which scenario most likely applies?

Answer options: ✅ Past performance is indicative of future performance for ETC

  • The original budget is no longer viable due to significant scope changes
  • The project is on track and within budget
  • The remaining work will be completed at the planned rate

Correct answer: Past performance is indicative of future performance for ETC

Explanation: This formula assumes that the actual cost incurred to date (AC) will be supplemented by the Estimate To Complete (ETC) based on project performance.

Start free practice for PMP (Project Management Professional)

200 questions · no signup required · 40 free questions per day

Start Practice →

More about PMP (Project Management Professional)

Related Questions

More for PMP (Project Management Professional) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free PMP (Project Management Professional) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.