What is the required sequence of operation to be verified for a Two-Stage system upon activation of a manual station?

In a two-stage system, activating a manual station should trigger the 'Alert' tone (1st stage), and the 'Evacuation' tone (2nd stage) should trigger after the p

Start free practice for ASTTBC RFPT — Fire Alarm Systems (AL)

30 questions · no signup required · 40 free questions per day

Start Practice →

Question: What is the required sequence of operation to be verified for a Two-Stage system upon activation of a manual station?

Answer options:

  • Instant 2nd stage evacuation throughout the building ✅ 1th Stage alert signal and start of the automatic timer for 2nd stage evacuation
  • Visual signals only until the fire department arrives
  • Voice communication only with no tones

Correct answer: 1th Stage alert signal and start of the automatic timer for 2nd stage evacuation

Explanation: In a two-stage system, activating a manual station should trigger the 'Alert' tone (1st stage), and the 'Evacuation' tone (2nd stage) should trigger after the programmed time or by key switch.

Start free practice for ASTTBC RFPT — Fire Alarm Systems (AL)

30 questions · no signup required · 40 free questions per day

Start Practice →

More about ASTTBC RFPT — Fire Alarm Systems (AL)

Related Questions

More for ASTTBC RFPT — Fire Alarm Systems (AL) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free ASTTBC RFPT — Fire Alarm Systems (AL) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.