ASTTBC RFPT — Fire Alarm Systems (AL) · Question
Which criterion must be met for the secondary power supply (batteries) during verification?
Clause 5.7.4.4 requires verifying that the battery capacity is sufficient to meet the design requirements, typically verified by a supervised discharge test or
Start free practice for ASTTBC RFPT — Fire Alarm Systems (AL)
30 questions · no signup required · 40 free questions per day
Question: Which criterion must be met for the secondary power supply (batteries) during verification?
Answer options:
- The battery is less than 5 years old ✅ The batteries can support the system for the duration required by the building code (e.g., 24h standby + 30m alarm)
- The battery voltage is exactly 24.0 VDC
- The battery is made in Canada
Correct answer: The batteries can support the system for the duration required by the building code (e.g., 24h standby + 30m alarm)
Explanation: Clause 5.7.4.4 requires verifying that the battery capacity is sufficient to meet the design requirements, typically verified by a supervised discharge test or calculation review.
Start free practice for ASTTBC RFPT — Fire Alarm Systems (AL)
30 questions · no signup required · 40 free questions per day
More about ASTTBC RFPT — Fire Alarm Systems (AL)
Related Questions
- Which of the following constitutes a system 'deficiency' rather than a 'non-conformance' to current standards?
- When a deficiency is corrected, what specific information MUST be recorded in the log?
- Which of the following would be categorized as a 'Non-Conformance' to the Installation Standard (S524) in an i
- In the event of a deficiency that renders the fire alarm system inoperative, what is the mandatory reporting r
- Where is the primary location for a set of Fire Alarm As-Built drawings in a commercial building?
- What is the most critical information that an 'As-Built' drawing provides compared to a 'Design' drawing?
More for ASTTBC RFPT — Fire Alarm Systems (AL) candidates
Study guides
FAQs
- How long is the ASTTBC RFPT Fire Alarm Systems (AL) exam? — ASTTBC RFPT Fire Alarm Systems (AL)
- How many questions are on the ASTTBC RFPT Fire Alarm Systems (AL) exam? — ASTTBC RFPT Fire Alarm Systems (AL)
- What is the passing score for the ASTTBC RFPT Fire Alarm Systems (AL) exam? — ASTTBC RFPT Fire Alarm Systems (AL)
- How often do I need to recertify ASTTBC RFPT Fire Alarm Systems (AL)? — ASTTBC RFPT Fire Alarm Systems (AL)
Question explanations
- Which of the following constitutes a system 'deficiency' rather than a 'non-conformance' to current standards?
- When a deficiency is corrected, what specific information MUST be recorded in the log?
- Which of the following would be categorized as a 'Non-Conformance' to the Installation Standard (S524) in an i
- In the event of a deficiency that renders the fire alarm system inoperative, what is the mandatory reporting r
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free ASTTBC RFPT — Fire Alarm Systems (AL) Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.