If the main control unit's CPU (central processing unit) is replaced with a newer version in an existing building, what is the testing scope?

If the main CPU or executive software is replaced, it is considered a major modification requiring 100% re-verification of the system.

Start free practice for ASTTBC RFPT — Fire Alarm Systems (AL)

30 questions · no signup required · 40 free questions per day

Start Practice →

Question: If the main control unit's CPU (central processing unit) is replaced with a newer version in an existing building, what is the testing scope?

Answer options: ✅ The entire fire alarm system must be re-verified

  • Only the first device on every circuit must be tested
  • Only the battery standby calculation needs to be updated
  • No testing is required if the model number of the CPU is identical

Correct answer: The entire fire alarm system must be re-verified

Explanation: If the main CPU or executive software is replaced, it is considered a major modification requiring 100% re-verification of the system.

Start free practice for ASTTBC RFPT — Fire Alarm Systems (AL)

30 questions · no signup required · 40 free questions per day

Start Practice →

More about ASTTBC RFPT — Fire Alarm Systems (AL)

Related Questions

More for ASTTBC RFPT — Fire Alarm Systems (AL) candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free ASTTBC RFPT — Fire Alarm Systems (AL) Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.