Carpenter Red Seal Exam Prep · Question
A project manager is reviewing a critical path analysis for a custom home build. The current critical path identifies 'Foundation Pour' (3 days) followed by 'Framing Ground Floor' (7 days). If both tasks are performed by different crews, and an issue causes the 'Foundation Pour' to extend by 2 days, what is the immediate impact on the start date of 'Framing Ground Floor'?
Since 'Framing Ground Floor' is scheduled to start immediately after 'Foundation Pour' and is on the critical path, an extension of the 'Foundation Pour' by 2 d
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A project manager is reviewing a critical path analysis for a custom home build. The current critical path identifies 'Foundation Pour' (3 days) followed by 'Framing Ground Floor' (7 days). If both tasks are performed by different crews, and an issue causes the 'Foundation Pour' to extend by 2 days, what is the immediate impact on the start date of 'Framing Ground Floor'?
Answer options:
- The 'Framing Ground Floor' will start 2 days earlier to compensate. ✅ The 'Framing Ground Floor' will start 2 days later.
- There will be no impact on the 'Framing Ground Floor' start date as they are different crews.
- The critical path will now extend by 5 days.
Correct answer: The 'Framing Ground Floor' will start 2 days later.
Explanation: Since 'Framing Ground Floor' is scheduled to start immediately after 'Foundation Pour' and is on the critical path, an extension of the 'Foundation Pour' by 2 days will directly delay the start of 'Framing Ground Floor' by the same amount. The critical path will also extend by 2 days, not 5.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.