Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cut 0.350 m' and the second stake, 5.0 m away, is marked 'Fill 0.150 m'. If the desired finished slab elevation is 102.500 m, what are the current ground elevations at both stakes?

For stake 1 (Cut 0.350 m), current ground elevation = desired slab elevation + cut = 102.500 m + 0.350 m = 102.850 m. For stake 2 (Fill 0.150 m), current ground

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

Question: Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cut 0.350 m' and the second stake, 5.0 m away, is marked 'Fill 0.150 m'. If the desired finished slab elevation is 102.500 m, what are the current ground elevations at both stakes?

Answer options: ✅ 102.850 m and 102.350 m

  • 102.150 m and 102.650 m
  • 102.850 m and 102.650 m
  • 102.150 m and 102.350 m

Correct answer: 102.850 m and 102.350 m

Explanation: For stake 1 (Cut 0.350 m), current ground elevation = desired slab elevation + cut = 102.500 m + 0.350 m = 102.850 m. For stake 2 (Fill 0.150 m), current ground elevation = desired slab elevation - fill = 102.500 m - 0.150 m = 102.350 m.

Start free practice for Carpenter Red Seal Exam Prep

300 questions · no signup required · 40 free questions per day

Start Practice →

More about Carpenter Red Seal Exam Prep

Related Questions

More for Carpenter Red Seal Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Carpenter Red Seal Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.