Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cut 0.350 m' and the second stake, 5.0 m away, is marked 'Fill 0.150 m'. If the desired finished slab elevation is 102.500 m, what are the current ground elevations at both stakes?
For stake 1 (Cut 0.350 m), current ground elevation = desired slab elevation + cut = 102.500 m + 0.350 m = 102.850 m. For stake 2 (Fill 0.150 m), current ground
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cut 0.350 m' and the second stake, 5.0 m away, is marked 'Fill 0.150 m'. If the desired finished slab elevation is 102.500 m, what are the current ground elevations at both stakes?
Answer options: ✅ 102.850 m and 102.350 m
- 102.150 m and 102.650 m
- 102.850 m and 102.650 m
- 102.150 m and 102.350 m
Correct answer: 102.850 m and 102.350 m
Explanation: For stake 1 (Cut 0.350 m), current ground elevation = desired slab elevation + cut = 102.500 m + 0.350 m = 102.850 m. For stake 2 (Fill 0.150 m), current ground elevation = desired slab elevation - fill = 102.500 m - 0.150 m = 102.350 m.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
- A surveyor's cut stake is marked 'C 0.65' for a road sub-grade. If the top of the stake is 0.20 m above the cu
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- What is the primary purpose of string lines and batter boards when laying out a foundation?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.