Carpenter Red Seal Exam Prep · Question
A carpenter is installing a pre-hung interior door and notices that the door slab is rubbing lightly on the hinge jamb. What is the most appropriate initial action to correct this issue?
If the door is rubbing on the hinge jamb, it indicates that the jamb is bowing in slightly at that point. Shimming behind the top hinge on the hinge jamb would
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is installing a pre-hung interior door and notices that the door slab is rubbing lightly on the hinge jamb. What is the most appropriate initial action to correct this issue?
Answer options:
- Remove the door from its frame and plane the rubbing edge of the door slab.
- Tighten the screws on the hinge leaves on the hinge jamb. ✅ Shim behind the top hinge on the hinge jamb to move the jamb slightly out.
- Shim behind the bottom hinge on the hinge jamb to move the jamb slightly in.
Correct answer: Shim behind the top hinge on the hinge jamb to move the jamb slightly out.
Explanation: If the door is rubbing on the hinge jamb, it indicates that the jamb is bowing in slightly at that point. Shimming behind the top hinge on the hinge jamb would push that portion of the jamb out, creating more clearance and correcting the rub. Planing the door is a last resort, and tightening screws or shimming the bottom hinge would not address the specific rub at the top.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.