Carpenter Red Seal Exam Prep · Question
When installing drywall on walls, how much gap should typically be left between the bottom edge of a drywall sheet and the subfloor or finished floor?
Leaving a gap of approximately 10 mm (3/8 inch) between the bottom of the drywall and the subfloor/finished floor is standard practice. This prevents moisture w
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: When installing drywall on walls, how much gap should typically be left between the bottom edge of a drywall sheet and the subfloor or finished floor?
Answer options:
- 5 mm (3/16 inch) ✅ 10 mm (3/8 inch)
- 2 mm (1/16 inch)
- 0 mm (resting directly on the floor)
Correct answer: 10 mm (3/8 inch)
Explanation: Leaving a gap of approximately 10 mm (3/8 inch) between the bottom of the drywall and the subfloor/finished floor is standard practice. This prevents moisture wicking from the floor, prevents damage from accidental kicks, and allows for minor building settlement without cracking the drywall. A smaller gap won't provide adequate protection, and resting directly on the floor can lead to moisture damage and cracking.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.