Carpenter Red Seal Exam Prep · Question
A carpenter is installing a pre-hung interior door unit into a rough opening. After shimming and fastening one side of the door jamb, the carpenter closes the door and notices that the reveal (gap) between the door slab and the jamb is wider at the top than at the bottom on the latch side. What is the most appropriate action to correct this issue?
If the reveal is wider at the top of the latch side, it indicates the bottom of the latch jamb is too far in. Adding shims behind the bottom of the latch jamb w
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is installing a pre-hung interior door unit into a rough opening. After shimming and fastening one side of the door jamb, the carpenter closes the door and notices that the reveal (gap) between the door slab and the jamb is wider at the top than at the bottom on the latch side. What is the most appropriate action to correct this issue?
Answer options:
- Add shims behind the top hinge on the hinge jamb.
- Remove shims from behind the bottom hinge on the hinge jamb. ✅ Add shims behind the bottom of the latch jamb.
- Remove shims from behind the top of the latch jamb.
Correct answer: Add shims behind the bottom of the latch jamb.
Explanation: If the reveal is wider at the top of the latch side, it indicates the bottom of the latch jamb is too far in. Adding shims behind the bottom of the latch jamb will push it outwards, equalizing the reveal. Adjusting the hinge side would primarily affect the door's swing and squareness to the frame, not necessarily the reveal on the latch side.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.