Carpenter Red Seal Exam Prep · Question
A carpenter is installing 20 mm thick subflooring panels. What is the recommended minimum gap to leave between the ends of the subfloor panels where they do not fall over a joist, but rather butt against each other?
A 3 mm gap, approximately the thickness of a 8d nail, should be left between the ends and edges of subfloor panels that do not have tongue-and-groove connection
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is installing 20 mm thick subflooring panels. What is the recommended minimum gap to leave between the ends of the subfloor panels where they do not fall over a joist, but rather butt against each other?
Answer options:
- 1 mm ✅ 3 mm
- 6 mm
- 10 mm
Correct answer: 3 mm
Explanation: A 3 mm gap, approximately the thickness of a 8d nail, should be left between the ends and edges of subfloor panels that do not have tongue-and-groove connections to allow for expansion due to changes in humidity and temperature. This prevents buckling and warping of the subfloor. Tongue-and-groove edges typically do not require this gap, as the joint itself accommodates movement.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.