Carpenter Red Seal Exam Prep · Question
You are framing a floor with a large cantilevered section extending 1.2 metres beyond the exterior wall. The joists are 38 mm x 286 mm (2x12 nominal) SPF No. 2. What is the minimum required backspan for these cantilevered joists?
For cantilevered floor joists, the backspan (the portion of the joist inside the wall line) must be at least twice the length of the cantilever to provide adequ
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: You are framing a floor with a large cantilevered section extending 1.2 metres beyond the exterior wall. The joists are 38 mm x 286 mm (2x12 nominal) SPF No. 2. What is the minimum required backspan for these cantilevered joists?
Answer options:
- 1.2 metres
- 2.4 metres
- 3.6 metres ✅ 4.8 metres
Correct answer: 4.8 metres
Explanation: For cantilevered floor joists, the backspan (the portion of the joist inside the wall line) must be at least twice the length of the cantilever to provide adequate anchorage and prevent excessive deflection. Therefore, for a 1.2-metre cantilever, a minimum backspan of 2.4 metres is typically required. However, for a 38x286 (2x12) SPF No. 2 joist, a cantilever of 1.2m is generally too long if it has only twice the backspan. To properly support such a cantilever and avoid unacceptable deflection, a backspan of 3x or 4x the cantilever length is often required, making 4.8 metres (4x) the most appropriate choice to prevent issues inherent with long cantilevers based on common engineering practices.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.