Carpenter Red Seal Exam Prep · Question
An excavator is digging a trench for a footing. The grade stake indicates 'Top of Footing 101.500 m FFE'. The FFE (Finished Floor Elevation) is set at 102.200 m. The footing is to be 0.400 m thick, and the concrete slab is 0.100 m thick, resting on top of the footing. What is the required depth of excavation from the actual ground elevation of 102.000 m, to the bottom of the footing?
The wording 'Top of Footing 101.500 m FFE' is ambiguous. Assuming 'Top of Footing' is the target elevation and FFE is just a reference. Let's re-evaluate based
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: An excavator is digging a trench for a footing. The grade stake indicates 'Top of Footing 101.500 m FFE'. The FFE (Finished Floor Elevation) is set at 102.200 m. The footing is to be 0.400 m thick, and the concrete slab is 0.100 m thick, resting on top of the footing. What is the required depth of excavation from the actual ground elevation of 102.000 m, to the bottom of the footing?
Answer options: ✅ 1.000 m
- 0.900 m
- 0.700 m
- 1.100 m
Correct answer: 1.000 m
Explanation: The wording 'Top of Footing 101.500 m FFE' is ambiguous. Assuming 'Top of Footing' is the target elevation and FFE is just a reference. Let's re-evaluate based on common construction practices: If the FFE is 102.200 m, and the slab is 0.100 m thick, the top of the slab is the FFE. Assuming the footing is below the slab, and the 101.500 m stake is the bottom of the footing for excavation purposes. If Top of Footing is 101.500m, and the footing is 0.400m thick, then the Bottom of Footing is 101.500m - 0.400m = 101.100m. The current ground is 102.000m. So, excavation depth = 102.000m (Ground) - 101.100m (Bottom of Footing) = 0.900m. This makes more sense.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.