Carpenter Red Seal Exam Prep · Question
A carpenter needs to frame a 2.4-metre wide opening for a patio door in an exterior wall carrying combined roof and floor loads. If using Laminated Veneer Lumber (LVL) with a depth of 240 mm, what is the minimum typical width (thickness) often referenced in span tables for this application, to satisfy bending and shear requirements?
For a 2.4-metre span with significant loads, a single 38 mm or 45 mm LVL might not be sufficient for stiffness or strength. A common and robust solution is ofte
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter needs to frame a 2.4-metre wide opening for a patio door in an exterior wall carrying combined roof and floor loads. If using Laminated Veneer Lumber (LVL) with a depth of 240 mm, what is the minimum typical width (thickness) often referenced in span tables for this application, to satisfy bending and shear requirements?
Answer options:
- 38 mm
- 45 mm ✅ 89 mm
- 130 mm
Correct answer: 89 mm
Explanation: For a 2.4-metre span with significant loads, a single 38 mm or 45 mm LVL might not be sufficient for stiffness or strength. A common and robust solution is often an 89 mm (3.5 inch nominal) LVL, or two thinner LVLs glued/nailed together, to meet or exceed header table requirements. Consult a specific LVL manufacturer's span tables, abiding by CSA O86.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.