Carpenter Red Seal Exam Prep · Question
A carpenter is setting grade stakes for a concrete slab pour that is 150 mm thick, and the finished floor elevation is 22.150 m. The benchmark is at 20.000 m. If the top of the grade stake is 22.000 m (elevation), what instruction should be written on the stake for the concrete finisher?
The desired slab soffit elevation is 22.150 m - 0.150 m = 22.000 m. Since the top of the stake is at 22.000 m, and this is the slab soffit elevation, no direct
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is setting grade stakes for a concrete slab pour that is 150 mm thick, and the finished floor elevation is 22.150 m. The benchmark is at 20.000 m. If the top of the grade stake is 22.000 m (elevation), what instruction should be written on the stake for the concrete finisher?
Answer options:
- ADD 150 mm ✅ FILL 150 mm
- Cut 150 mm
- ADD 300 mm
Correct answer: FILL 150 mm
Explanation: The desired slab soffit elevation is 22.150 m - 0.150 m = 22.000 m. Since the top of the stake is at 22.000 m, and this is the slab soffit elevation, no direct cut/fill for sub-grade preparation is needed. However, if the stake was meant to be for the finished concrete surface, and the stake top is at slab soffit, then 150 mm of fill (concrete) is needed to reach the finished grade. The question implies the instruction for the finisher to reach slab top: 22.150 (F.F.L.) - 22.000 (stake top) = 0.150 m = 150 mm of concrete on top of the stake. So a common instruction would be 'FILL 150 mm' indicating the thickness of concrete above that subgrade point (stake top).
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.