Carpenter Red Seal Exam Prep · Question
A carpenter is setting up a wall formwork system for a 3.0 m high concrete pour. The concrete has a density of 2400 kg/m³. What is the maximum horizontal pressure exerted by the wet concrete at the base of the formwork, assuming a fluid pressure calculation (P = ρgh)?
The maximum horizontal pressure (P) at the base of the formwork is calculated using the formula P = ρgh, where ρ (rho) is the density of concrete (2400 kg/m³),
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is setting up a wall formwork system for a 3.0 m high concrete pour. The concrete has a density of 2400 kg/m³. What is the maximum horizontal pressure exerted by the wet concrete at the base of the formwork, assuming a fluid pressure calculation (P = ρgh)?
Answer options:
- 24.0 kPa
- 70.6 kPa ✅ 72.0 kPa
- 80.0 kPa
Correct answer: 72.0 kPa
Explanation: The maximum horizontal pressure (P) at the base of the formwork is calculated using the formula P = ρgh, where ρ (rho) is the density of concrete (2400 kg/m³), g is the acceleration due to gravity (approximately 9.81 m/s²), and h is the height of the pour (3.0 m). So, P = 2400 kg/m³ * 9.81 m/s² * 3.0 m = 70,632 Pa or approximately 70.6 kPa. The closest provided option is 72.0 kPa which implies g=10m/s^2.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.