Carpenter Red Seal Exam Prep · Question
A carpenter is setting up a series of 5.0 m tall timber shores for a suspended slab. What is the minimum recommended bracing configuration to ensure adequate stability for these shores, assuming standard timber dimensions?
For shores exceeding 3.0 m, CSA S269.3 requires diagonal bracing in both directions, with the unbraced length of the timber shore not exceeding 40 times its lea
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A carpenter is setting up a series of 5.0 m tall timber shores for a suspended slab. What is the minimum recommended bracing configuration to ensure adequate stability for these shores, assuming standard timber dimensions?
Answer options:
- Bracing only at the top of the shores. ✅ Diagonal bracing in both directions, at a maximum unbraced length of 2.0 m.
- Horizontal bracing at mid-height only.
- No bracing is required if the shores are plumb.
Correct answer: Diagonal bracing in both directions, at a maximum unbraced length of 2.0 m.
Explanation: For shores exceeding 3.0 m, CSA S269.3 requires diagonal bracing in both directions, with the unbraced length of the timber shore not exceeding 40 times its least dimension. A 2.0 m unbraced length is a common and safe practice for tall shores, providing sufficient lateral stability and preventing buckling, often resulting in multiple bracing levels.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.