Carpenter Red Seal Exam Prep · Question
A builder wants to achieve an effective RSI of 4.5 m²·K/W in a 38x140 mm (2x6) exterior wall in British Columbia. If batt insulation with an RSI of 3.2 m²·K/W per 100 mm is chosen, what approximate thickness of continuous exterior rigid insulation (RSI 0.75 m²·K/W per 25 mm) would be required to compensate for a 15% framing factor?
This requires a step-by-step calculation to account for internal stud-cavity insulation and the added exterior insulation, while considering the thermal bridgin
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A builder wants to achieve an effective RSI of 4.5 m²·K/W in a 38x140 mm (2x6) exterior wall in British Columbia. If batt insulation with an RSI of 3.2 m²·K/W per 100 mm is chosen, what approximate thickness of continuous exterior rigid insulation (RSI 0.75 m²·K/W per 25 mm) would be required to compensate for a 15% framing factor?
Answer options: ✅ 50 mm
- 75 mm
- 100 mm
- 125 mm
Correct answer: 50 mm
Explanation: This requires a step-by-step calculation to account for internal stud-cavity insulation and the added exterior insulation, while considering the thermal bridging effect. The overall effective RSI calculation is complex, but approximately 50mm of rigid insulation helps bridge the gap to 4.5 by reducing thermal bridging.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.