Carpenter Red Seal Exam Prep · Question
A wall assembly in Vancouver (mild climate) uses 38x89 mm (2x4) studs and has a total clear-wall RSI of 3.0 m²·K/W. If a client wants to upgrade the insulation from R-12 batt (125 mm thickness, RSI 2.1 m²·K/W) to R-20 batt (140 mm thickness, RSI 3.5 m²·K/W) and add an exterior layer of 25 mm rigid insulation (RSI 0.75 m²·K/W), what would be the approximate new clear-wall RSI value, assuming negligible change in film resistances and sheathing?
The original clear-wall RSI is 3.0. The insulation upgrade from R-12 (RSI 2.1) to R-20 (RSI 3.5) changes the cavity insulation component by 3.5 - 2.1 = 1.4. Add
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A wall assembly in Vancouver (mild climate) uses 38x89 mm (2x4) studs and has a total clear-wall RSI of 3.0 m²·K/W. If a client wants to upgrade the insulation from R-12 batt (125 mm thickness, RSI 2.1 m²·K/W) to R-20 batt (140 mm thickness, RSI 3.5 m²·K/W) and add an exterior layer of 25 mm rigid insulation (RSI 0.75 m²·K/W), what would be the approximate new clear-wall RSI value, assuming negligible change in film resistances and sheathing?
Answer options:
- RSI 3.8 m²·K/W ✅ RSI 4.1 m²·K/W
- RSI 4.6 m²·K/W
- RSI 5.0 m²·K/W
Correct answer: RSI 4.1 m²·K/W
Explanation: The original clear-wall RSI is 3.0. The insulation upgrade from R-12 (RSI 2.1) to R-20 (RSI 3.5) changes the cavity insulation component by 3.5 - 2.1 = 1.4. Adding 25 mm rigid insulation (RSI 0.75) directly adds to this. So, 3.0 (original) - 2.1 (old batt) + 3.5 (new batt) + 0.75 (rigid) = 4.15. The clear wall calculation primarily involves summing layer RSIs.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.