Carpenter Red Seal Exam Prep · Question
A crawl space in a cold climate requires moisture control. Which option describes the most appropriate vapour barrier strategy for the ground beneath the crawl space?
A 6-mil polyethylene sheet with properly overlapped and taped seams, extending up the foundation walls, provides an effective vapour barrier over the soil in a
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: A crawl space in a cold climate requires moisture control. Which option describes the most appropriate vapour barrier strategy for the ground beneath the crawl space?
Answer options:
- No vapour barrier is needed; natural ventilation will handle moisture.
- A woven geotextile fabric directly on the soil, covered with gravel. ✅ A 6-mil (0.15 mm) polyethylene sheet, overlapping seams by 300 mm and taped, extending up foundation walls.
- A thin, breathable membrane that allows soil moisture to escape upwards.
Correct answer: A 6-mil (0.15 mm) polyethylene sheet, overlapping seams by 300 mm and taped, extending up foundation walls.
Explanation: A 6-mil polyethylene sheet with properly overlapped and taped seams, extending up the foundation walls, provides an effective vapour barrier over the soil in a crawl space. This prevents ground moisture from evaporating into the crawl space air, reducing humidity and potential condensation issues in the structure above, as per NBC 2020 guidelines for ground covers.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.