Carpenter Red Seal Exam Prep · Question
When setting up temporary shoring for a 4.0 m long header over a new opening, the shoring posts should be placed at a maximum spacing. According to CSA S269.1-16 'Concrete Formwork', what is the common practice for maximum shoring post spacing to adequately support temporary loads?
While CSA S269.1-16 primarily deals with formwork, general construction practice for temporary shoring and falsework often uses a maximum spacing of 0.9 m (3 ft
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: When setting up temporary shoring for a 4.0 m long header over a new opening, the shoring posts should be placed at a maximum spacing. According to CSA S269.1-16 'Concrete Formwork', what is the common practice for maximum shoring post spacing to adequately support temporary loads?
Answer options:
- 0.6 m (2 ft) ✅ 0.9 m (3 ft)
- 1.2 m (4 ft)
- 1.8 m (6 ft)
Correct answer: 0.9 m (3 ft)
Explanation: While CSA S269.1-16 primarily deals with formwork, general construction practice for temporary shoring and falsework often uses a maximum spacing of 0.9 m (3 ft) for standard dimensional lumber walers and joists to ensure adequate load distribution and prevent excessive deflection.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.