Carpenter Red Seal Exam Prep · Question
You are planning to remove a 2.0 m section of an interior wall on the main floor of a single-storey house with a conventional framed roof. You notice the ceiling joists run parallel to this wall. What does this observation MOST strongly suggest about the wall's function?
If ceiling joists run parallel to a wall, the wall is generally not directly supporting the ends or middles of those joists, which indicates it's likely a non-l
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: You are planning to remove a 2.0 m section of an interior wall on the main floor of a single-storey house with a conventional framed roof. You notice the ceiling joists run parallel to this wall. What does this observation MOST strongly suggest about the wall's function?
Answer options:
- It is definitely load-bearing and requires a beam. ✅ It is likely non-load-bearing, serving as a partition wall.
- It is impossible to tell without seeing the foundation.
- It is a shear wall for seismic resistance.
Correct answer: It is likely non-load-bearing, serving as a partition wall.
Explanation: If ceiling joists run parallel to a wall, the wall is generally not directly supporting the ends or middles of those joists, which indicates it's likely a non-load-bearing partition wall, only supporting its own weight and finishes. Load-bearing walls typically run perpendicular to supported joists.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.