Carpenter Red Seal Exam Prep · Question
You need to temporarily shore a 3.6 m (12 ft) span where you've cut a large opening in a load-bearing wall. The floor system above consists of 38 mm x 235 mm (2x10) joists at 400 mm (16 in) centres over the opening. What is the MINIMUM recommended number of temporary shoring posts needed for practical and safe support across this span, considering a common shoring beam arrangement?
For a 3.6 m span, to effectively support the load, shoring posts should typically not exceed 1.2 m (4 ft) spacing, often closer. Therefore, with a common shorin
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
Question: You need to temporarily shore a 3.6 m (12 ft) span where you've cut a large opening in a load-bearing wall. The floor system above consists of 38 mm x 235 mm (2x10) joists at 400 mm (16 in) centres over the opening. What is the MINIMUM recommended number of temporary shoring posts needed for practical and safe support across this span, considering a common shoring beam arrangement?
Answer options:
- 2 posts
- 3 posts ✅ 4 posts
- 5 posts
Correct answer: 4 posts
Explanation: For a 3.6 m span, to effectively support the load, shoring posts should typically not exceed 1.2 m (4 ft) spacing, often closer. Therefore, with a common shoring beam running under the joists, a minimum of 4 posts (one at each end and two intermediate) would be required to divide the span into roughly three equal sections (e.g., ~1.2m spacing) providing adequate and stable support for the overhead structure as per good carpentry practice.
Start free practice for Carpenter Red Seal Exam Prep
300 questions · no signup required · 40 free questions per day
More about Carpenter Red Seal Exam Prep
Related Questions
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
- What is the primary purpose of string lines and batter boards when laying out a foundation?
- According to typical blueprint conventions, a heavily dashed line (longer dashes) often represents an item tha
More for Carpenter Red Seal Exam Prep candidates
Practice tests
Question explanations
- When interpreting a foundation plan, a dashed line with 'P. WALL' typically represents which of the following?
- A site plan shows contour lines with an interval of 0.5 m. If two adjacent contour lines are labelled 124.0 m
- According to the National Building Code of Canada (NBC) 2020, what is the primary consideration for the requir
- Two offset stakes are driven at 2.0 m from the proposed edge of a concrete slab. The first stake is marked 'Cu
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Carpenter Red Seal Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.