Crane Operator Certification Exam Prep · Question
An 80-tonne mobile crane is being used for a lift. The wind speed, measured at the boom tip, is consistently 45 km/h. According to CSA Z150, what action should the crane operator take?
CSA Z150 generally specifies that crane operations, particularly with mobile cranes, should cease when wind speeds at the boom tip exceed 48 km/h (30 mph), or b
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
Question: An 80-tonne mobile crane is being used for a lift. The wind speed, measured at the boom tip, is consistently 45 km/h. According to CSA Z150, what action should the crane operator take?
Answer options:
- Continue the lift with caution, as this speed is acceptable.
- Reduce the load to account for wind forces and continue the lift. ✅ Immediately cease crane operations until the wind subsides.
- Orient the boom directly into the wind to minimize surface area.
Correct answer: Immediately cease crane operations until the wind subsides.
Explanation: CSA Z150 generally specifies that crane operations, particularly with mobile cranes, should cease when wind speeds at the boom tip exceed 48 km/h (30 mph), or based on the manufacturer's recommendations if lower. Since 45 km/h is approaching or at the limit for many cranes, and safety is paramount, ceasing operations is the safest action. Reducing the load might not be sufficient, and orienting the boom is not a universal solution.
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
More about Crane Operator Certification Exam Prep
Related Questions
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
- What is the purpose of an anti-two-block device on a crane?
- Why is it important to keep the load as close to the ground as possible when moving it with a crane?
More for Crane Operator Certification Exam Prep candidates
Question explanations
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Crane Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.