According to CSA Z150, when should a ground bearing pressure calculation be performed?

CSA Z150 Clause 5.2.1 states that the ground conditions shall be assessed and calculations performed to ensure the ground can support the crane and its load for

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

Question: According to CSA Z150, when should a ground bearing pressure calculation be performed?

Answer options:

  • Only for lifts exceeding 75% of the crane's capacity. ✅ Prior to every crane setup where outriggers are used and ground conditions are unknown or questionable.
  • Only when lifting suspended personnel platforms.
  • Upon completion of the lift, to verify stability.

Correct answer: Prior to every crane setup where outriggers are used and ground conditions are unknown or questionable.

Explanation: CSA Z150 Clause 5.2.1 states that the ground conditions shall be assessed and calculations performed to ensure the ground can support the crane and its load for any setup where outriggers are used and ground conditions are unknown or appear insufficient.

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

More about Crane Operator Certification Exam Prep

Related Questions

More for Crane Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Crane Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.