A mobile crane is operating near a 13.8 kV overhead power line. According to CSA Z150, what is the minimum required clearance distance between any part of the crane, including its load, and this energized power line?
CSA Z150 Table 1, 'Minimum Clearance from Overhead Electrical Conductors', specifies a 4.5-metre clearance for lines rated over 750 V to 75 kV. This is a crucia
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
Question: A mobile crane is operating near a 13.8 kV overhead power line. According to CSA Z150, what is the minimum required clearance distance between any part of the crane, including its load, and this energized power line?
Answer options: ✅ 4.5 metres
- 3.0 metres
- 6.0 metres
- 7.5 metres
Correct answer: 4.5 metres
Explanation: CSA Z150 Table 1, 'Minimum Clearance from Overhead Electrical Conductors', specifies a 4.5-metre clearance for lines rated over 750 V to 75 kV. This is a crucial safety distance to prevent electrocution.
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
More about Crane Operator Certification Exam Prep
Related Questions
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
- What is the purpose of an anti-two-block device on a crane?
- Why is it important to keep the load as close to the ground as possible when moving it with a crane?
More for Crane Operator Certification Exam Prep candidates
Question explanations
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Crane Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.