A crane operator is using a two-part reeving system. After completing a lift, the operator slowly lowers the block without a load. While doing so, the hoist limit switch activates repeatedly, and the block occasionally bumps against the boom tip. What immediate action should the operator take and why?
Repeated limit switch activation and bumping indicate a high risk of catastrophic two-blocking. The operator must immediately stop, investigate the reason for t
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
Question: A crane operator is using a two-part reeving system. After completing a lift, the operator slowly lowers the block without a load. While doing so, the hoist limit switch activates repeatedly, and the block occasionally bumps against the boom tip. What immediate action should the operator take and why?
Answer options:
- Continue lowering slowly, as it's just the empty block.
- Increase engine RPM to speed up the descent and clear the switch. ✅ Stop lowering, identify the cause of limit switch activation, and inspect for two-blocking risk.
- Engage the boom auxiliary hoist to create more clearance.
Correct answer: Stop lowering, identify the cause of limit switch activation, and inspect for two-blocking risk.
Explanation: Repeated limit switch activation and bumping indicate a high risk of catastrophic two-blocking. The operator must immediately stop, investigate the reason for the switch activation, and ensure there is adequate distance between the block and boom tip to prevent damage.
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
More about Crane Operator Certification Exam Prep
Related Questions
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
- What is the purpose of an anti-two-block device on a crane?
- Why is it important to keep the load as close to the ground as possible when moving it with a crane?
More for Crane Operator Certification Exam Prep candidates
Question explanations
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Crane Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.