A crane's load chart, for a particular boom length and radius, shows a rated capacity of 10,000 kg. The operator intends to lift a precast beam weighing 8,500 kg. The rigging setup includes a 400 kg main hoist block, 100 kg of wire rope reeved on the block, and 250 kg of slings and shackles. What is the percentage of the remaining available capacity after accounting for the load and deductions?
First, calculate total deductions: 400 kg (block) + 100 kg (reeving) + 250 kg (rigging) = 750 kg. Then, calculate the total weight acting on the crane: 8,500 kg
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
Question: A crane's load chart, for a particular boom length and radius, shows a rated capacity of 10,000 kg. The operator intends to lift a precast beam weighing 8,500 kg. The rigging setup includes a 400 kg main hoist block, 100 kg of wire rope reeved on the block, and 250 kg of slings and shackles. What is the percentage of the remaining available capacity after accounting for the load and deductions?
Answer options: ✅ 7.5%
- 15.0%
- 10.0%
- 5.0%
Correct answer: 7.5%
Explanation: First, calculate total deductions: 400 kg (block) + 100 kg (reeving) + 250 kg (rigging) = 750 kg. Then, calculate the total weight acting on the crane: 8,500 kg (load) + 750 kg (deductions) = 9,250 kg. The remaining available capacity is 10,000 kg - 9,250 kg = 750 kg. As a percentage: (750 kg / 10,000 kg) * 100% = 7.5%.
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
More about Crane Operator Certification Exam Prep
Related Questions
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
- What is the purpose of an anti-two-block device on a crane?
- Why is it important to keep the load as close to the ground as possible when moving it with a crane?
More for Crane Operator Certification Exam Prep candidates
Question explanations
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Crane Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.