Crane Operator Certification Exam Prep · Question

A crane operator is assigned a lift involving 85% of the crane's rated capacity for the given configuration. According to CSA Z150, what is required before proceeding?

CSA Z150-13, Clause 5.3.3.1 states that any lift exceeding 75% of the rated capacity is considered a critical lift and requires a specific critical lift plan to

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

Question: A crane operator is assigned a lift involving 85% of the crane's rated capacity for the given configuration. According to CSA Z150, what is required before proceeding?

Answer options: ✅ A critical lift plan must be developed and approved.

  • The lift must be re-evaluated to reduce the load or increase the crane's capacity.
  • A pre-shift meeting with all personnel involved in the lift is sufficient.
  • The lift can proceed with enhanced communication protocols.

Correct answer: A critical lift plan must be developed and approved.

Explanation: CSA Z150-13, Clause 5.3.3.1 states that any lift exceeding 75% of the rated capacity is considered a critical lift and requires a specific critical lift plan to ensure safety and account for all variables.

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

More about Crane Operator Certification Exam Prep

Related Questions

More for Crane Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Crane Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.