Crane Operator Certification Exam Prep · Question
During a pre-shift inspection, a crane operator discovers that the safety latch on the main load hook is missing. What is the immediate action required based on Canadian OHS crane regulations?
CSA Z150 and provincial OHS regulations, such as Ontario Reg. 213/91 for construction projects, explicitly state that components with defects affecting safe ope
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
Question: During a pre-shift inspection, a crane operator discovers that the safety latch on the main load hook is missing. What is the immediate action required based on Canadian OHS crane regulations?
Answer options:
- Secure the load with additional slings to compensate for the missing latch. ✅ Tag out the crane and report the defect immediately; the hook must not be used.
- Continue operations with lighter loads until a replacement latch can be installed.
- Use caution and ensure the rigging crew maintains visual contact with the hook.
Correct answer: Tag out the crane and report the defect immediately; the hook must not be used.
Explanation: CSA Z150 and provincial OHS regulations, such as Ontario Reg. 213/91 for construction projects, explicitly state that components with defects affecting safe operation, like a missing or damaged hook safety latch, must render the equipment out of service. Tagging out the crane prevents its unauthorized use and ensures the defect is addressed before resuming operations, protecting personnel from accidental load disengagement.
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
More about Crane Operator Certification Exam Prep
Related Questions
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
- What is the purpose of an anti-two-block device on a crane?
- Why is it important to keep the load as close to the ground as possible when moving it with a crane?
More for Crane Operator Certification Exam Prep candidates
Question explanations
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Crane Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.