Before commencing a critical lift, the designated competent person should review the lift plan. What is a key element of the lift plan relevant to load balancing?

A critical lift plan must detail the load's centre of gravity and the proposed rigging to ensure stability and proper load balancing throughout the lift.

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

Question: Before commencing a critical lift, the designated competent person should review the lift plan. What is a key element of the lift plan relevant to load balancing?

Answer options:

  • The crane's maximum travel speed on site.
  • The estimated time for the lift duration. ✅ The location of the load's centre of gravity and the proposed rigging arrangement.
  • The daily weather forecast from an external source.

Correct answer: The location of the load's centre of gravity and the proposed rigging arrangement.

Explanation: A critical lift plan must detail the load's centre of gravity and the proposed rigging to ensure stability and proper load balancing throughout the lift.

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

More about Crane Operator Certification Exam Prep

Related Questions

More for Crane Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Crane Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.