A tower crane operator observes the anemometer displaying a sustained wind speed of 65 km/h (40 mph). The crane's operational wind speed limit, as per the manufacturer's chart and site-specific wind plan, is 60 km/h (37 mph). What is the most appropriate action the operator should take?
Exceeding the manufacturer's specified operational wind speed limit, or the more restrictive site-specific limit, requires immediate cessation of lifting operat
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
Question: A tower crane operator observes the anemometer displaying a sustained wind speed of 65 km/h (40 mph). The crane's operational wind speed limit, as per the manufacturer's chart and site-specific wind plan, is 60 km/h (37 mph). What is the most appropriate action the operator should take?
Answer options:
- Continue operations cautiously, as the difference is minor and temporary. ✅ Immediately cease lifting operations and secure the crane in accordance with the site wind plan.
- Reduce the load weight and hoist speed, then continue operations.
- Inform the signal person and wait for their instruction before proceeding.
Correct answer: Immediately cease lifting operations and secure the crane in accordance with the site wind plan.
Explanation: Exceeding the manufacturer's specified operational wind speed limit, or the more restrictive site-specific limit, requires immediate cessation of lifting operations and securing the crane to prevent overturning or damage. Continuing to operate under such conditions is a significant safety hazard.
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
More about Crane Operator Certification Exam Prep
Related Questions
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
- What is the purpose of an anti-two-block device on a crane?
- Why is it important to keep the load as close to the ground as possible when moving it with a crane?
More for Crane Operator Certification Exam Prep candidates
Question explanations
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Crane Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.