Crane Operator Certification Exam Prep · Question
During a multi-crane lift to install a 50-metre (164 ft) steel truss, two cranes are required to collaboratively hoist the load. According to CSA Z150-16, what is the primary consideration when determining the load distribution between the two cranes?
When two or more cranes are used to lift a load, the portion of the load to be handled by any one crane shall not exceed 80% of the rated capacity of that crane
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
Question: During a multi-crane lift to install a 50-metre (164 ft) steel truss, two cranes are required to collaboratively hoist the load. According to CSA Z150-16, what is the primary consideration when determining the load distribution between the two cranes?
Answer options:
- Ensuring the largest crane carries at least 75% of the total load. ✅ Each crane's share of the load must not exceed 80% of its rated capacity for the specific configuration.
- Distributing the load equally between the two cranes regardless of their individual capacities.
- The total weight of the truss must be less than the sum of the cranes' minimum hook heights.
Correct answer: Each crane's share of the load must not exceed 80% of its rated capacity for the specific configuration.
Explanation: When two or more cranes are used to lift a load, the portion of the load to be handled by any one crane shall not exceed 80% of the rated capacity of that crane for the radius and configuration being used. This safety margin (80% rule) is a critical requirement in multi-crane operations to account for dynamic loading and minor imbalances, as per CSA Z150-16 Section 5.1.7.3.
Start free practice for Crane Operator Certification Exam Prep
404 questions · no signup required · 40 free questions per day
More about Crane Operator Certification Exam Prep
Related Questions
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
- What is the purpose of an anti-two-block device on a crane?
- Why is it important to keep the load as close to the ground as possible when moving it with a crane?
More for Crane Operator Certification Exam Prep candidates
Question explanations
- According to most Canadian provincial regulations, who is ultimately responsible for the safe operation of a c
- A crane's rated capacity decreases as the load radius:
- What is the minimum number of full wraps of wire rope that must remain on a hoist drum when the hook is in its
- Before setting up a mobile crane, what is the most important factor to assess regarding ground conditions?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Crane Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.