During a daily crane inspection, what condition would necessitate immediate removal of a wire rope from service?

According to CSA Z150, a wire rope must be removed from service if there are more than six randomly distributed broken wires in one rope lay, or three broken wi

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

Question: During a daily crane inspection, what condition would necessitate immediate removal of a wire rope from service?

Answer options:

  • Slight surface rust on an infrequently used section.
  • A single broken wire in an outer strand.
  • Accumulation of dirt and grease. ✅ More than six randomly distributed broken wires in one rope lay, or three broken wires in one strand in one lay.

Correct answer: More than six randomly distributed broken wires in one rope lay, or three broken wires in one strand in one lay.

Explanation: According to CSA Z150, a wire rope must be removed from service if there are more than six randomly distributed broken wires in one rope lay, or three broken wires in one strand in one rope lay, as this indicates a significant loss of strength.

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

More about Crane Operator Certification Exam Prep

Related Questions

More for Crane Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Crane Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.