According to CSA Z150 standards, what is the minimum required clearance distance for crane operation near a 750 kV power line?

CSA Z150-16 specifies a minimum clearance of 7.5 metres for power lines operating between 250 kV and 750 kV.

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

Question: According to CSA Z150 standards, what is the minimum required clearance distance for crane operation near a 750 kV power line?

Answer options:

  • 3.0 metres (10 feet)
  • 4.5 metres (15 feet)
  • 6.0 metres (20 feet) ✅ 7.5 metres (25 feet)

Correct answer: 7.5 metres (25 feet)

Explanation: CSA Z150-16 specifies a minimum clearance of 7.5 metres for power lines operating between 250 kV and 750 kV.

Start free practice for Crane Operator Certification Exam Prep

404 questions · no signup required · 40 free questions per day

Start Practice →

More about Crane Operator Certification Exam Prep

Related Questions

More for Crane Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Crane Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.