A trench in Type 4 soil (saturated, fine-grained soil) is planned to be 3.0 metres deep. According to Ontario regulations, what is the minimum slope ratio (vertical to horizontal) that must be applied to the trench walls if a protective system other than shoring is used?

Ontario Regulation 213/91, Section 234(3) states that for Type 4 soil, the maximum slope of the face of an excavation must not exceed 1 vertical to 3 horizontal

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

Question: A trench in Type 4 soil (saturated, fine-grained soil) is planned to be 3.0 metres deep. According to Ontario regulations, what is the minimum slope ratio (vertical to horizontal) that must be applied to the trench walls if a protective system other than shoring is used?

Answer options:

  • 1 vertical to 1 horizontal
  • 1 vertical to 1.5 horizontal
  • 1 vertical to 2 horizontal ✅ 1 vertical to 3 horizontal

Correct answer: 1 vertical to 3 horizontal

Explanation: Ontario Regulation 213/91, Section 234(3) states that for Type 4 soil, the maximum slope of the face of an excavation must not exceed 1 vertical to 3 horizontal. This significantly flatter slope is necessary due to the instability of Type 4 soil.

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

More about Excavator Operator Certification Exam Prep

Related Questions

More for Excavator Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Excavator Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.