What is the primary factor that distinguishes Type 2 soil from Type 3 soil under Canadian OHS regulations for excavation classification?
The primary distinction between soil types (e.g., Type 2 'compacted' vs. Type 3 'granular non-cohesive') lies in their unconfined compressive strength and cohes
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: What is the primary factor that distinguishes Type 2 soil from Type 3 soil under Canadian OHS regulations for excavation classification?
Answer options:
- The presence of groundwater.
- The size of the aggregate particles. ✅ The soil's unconfined compressive strength and cohesion.
- The colour and organic content of the soil.
Correct answer: The soil's unconfined compressive strength and cohesion.
Explanation: The primary distinction between soil types (e.g., Type 2 'compacted' vs. Type 3 'granular non-cohesive') lies in their unconfined compressive strength and cohesive properties, which dictate their stability and resistance to collapse.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.