A trench is being excavated in soil determined to be Type 4. The trench is 2.0 metres deep. If a simple sloping method is chosen, what is the minimum horizontal dimension required for the sloped portion of the trench wall (from the bottom edge of the trench to the top edge at ground level) as per Ontario regulations?

For Type 4 soil, Ontario Regulation 213/91 Section 234(3) mandates a maximum slope of 1 vertical to 3 horizontal. Therefore, for a 2.0m deep trench, the horizon

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

Question: A trench is being excavated in soil determined to be Type 4. The trench is 2.0 metres deep. If a simple sloping method is chosen, what is the minimum horizontal dimension required for the sloped portion of the trench wall (from the bottom edge of the trench to the top edge at ground level) as per Ontario regulations?

Answer options:

  • 2.0 metres (1:1 slope)
  • 3.0 metres (1:1.5 slope)
  • 4.0 metres (1:2 slope) ✅ 6.0 metres (1:3 slope)

Correct answer: 6.0 metres (1:3 slope)

Explanation: For Type 4 soil, Ontario Regulation 213/91 Section 234(3) mandates a maximum slope of 1 vertical to 3 horizontal. Therefore, for a 2.0m deep trench, the horizontal dimension required is 2.0m x 3 = 6.0 metres.

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

More about Excavator Operator Certification Exam Prep

Related Questions

More for Excavator Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Excavator Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.