An excavator is trenching for a new water line with a maximum depth of 2.5 metres. According to Ontario O. Reg. 213/91, what is the minimum required distance from the edge of the trench that excavated material (spoil pile) must be placed?
Ontario O. Reg. 213/91, Section 228 (1) states that excavated material shall be kept at least 1 metre from the edge of the trench. This mitigates surcharge load
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: An excavator is trenching for a new water line with a maximum depth of 2.5 metres. According to Ontario O. Reg. 213/91, what is the minimum required distance from the edge of the trench that excavated material (spoil pile) must be placed?
Answer options: ✅ 1.0 metre
- 0.6 metres
- 0.5 metres
- 1.2 metres
Correct answer: 1.0 metre
Explanation: Ontario O. Reg. 213/91, Section 228 (1) states that excavated material shall be kept at least 1 metre from the edge of the trench. This mitigates surcharge loading on the trench wall and prevents material from falling back into the excavation.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.