An excavator operator is digging a trench in a Type 1 soil. What minimum distance must the spoil pile be kept from the edge of the excavation to prevent collapse, according to general safety guidelines?
OHS regulations across Canada (e.g., Ontario O. Reg. 213/91 Section 232(3)) generally require spoil piles to be kept at a minimum distance of 0.6 metres (2 feet
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: An excavator operator is digging a trench in a Type 1 soil. What minimum distance must the spoil pile be kept from the edge of the excavation to prevent collapse, according to general safety guidelines?
Answer options: ✅ 0.5 metres
- 0.6 metres
- 1.0 metre
- 1.2 metres
Correct answer: 0.5 metres
Explanation: OHS regulations across Canada (e.g., Ontario O. Reg. 213/91 Section 232(3)) generally require spoil piles to be kept at a minimum distance of 0.6 metres (2 feet) from the edge of an excavation, regardless of soil type, to prevent added surcharge load.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.