An excavator is operating on a site where overhead powerlines are present. The operator needs to dig near a pole for a new foundation. The lines are visibly slack, indicating they might be de-energized. What is the correct protocol before commencing work?
All powerlines must be treated as energized until the utility company has confirmed they are de-energized and grounded. Visual inspection is insufficient. Obtai
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: An excavator is operating on a site where overhead powerlines are present. The operator needs to dig near a pole for a new foundation. The lines are visibly slack, indicating they might be de-energized. What is the correct protocol before commencing work?
Answer options:
- Proceed with extreme caution, assuming they are live until visually confirmed otherwise. ✅ Contact the utility company to verify the lines are de-energized and grounded, and obtain a work permit if required.
- Have a qualified electrician inspect the lines on-site for voltage.
- Maintain the 3-metre clearance as a precaution, even if they appear de-energized.
Correct answer: Contact the utility company to verify the lines are de-energized and grounded, and obtain a work permit if required.
Explanation: All powerlines must be treated as energized until the utility company has confirmed they are de-energized and grounded. Visual inspection is insufficient. Obtaining a work permit and clearance from the utility is mandatory to ensure worker safety, as per OHS regulations concerning electrical hazards (e.g., Ont. Reg. 213/91, Section 188).
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.