A trench is being backfilled with granular material that requires compaction every 300 mm lift. The trench is 3.0 metres deep. How many compaction passes are required for the full depth of backfill?

To calculate the number of compaction passes, divide the total depth by the lift thickness: 3.0 metres / 0.300 metres = 10 layers. Therefore, 10 compaction pass

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

Question: A trench is being backfilled with granular material that requires compaction every 300 mm lift. The trench is 3.0 metres deep. How many compaction passes are required for the full depth of backfill?

Answer options: ✅ 10 passes

  • 9 passes
  • 11 passes
  • 12 passes

Correct answer: 10 passes

Explanation: To calculate the number of compaction passes, divide the total depth by the lift thickness: 3.0 metres / 0.300 metres = 10 layers. Therefore, 10 compaction passes are required for the full depth.

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

More about Excavator Operator Certification Exam Prep

Related Questions

More for Excavator Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Excavator Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.