A granular pipe bedding material needs to be compacted to 95% Standard Proctor Density. The specified lift thickness for this material is 150 mm. If the pipe invert is 2 metres below existing grade, and 300 mm of bedding is required below the pipe, how many lifts of bedding material are needed?
If 300 mm of bedding is required below pipe, and each lift is 150 mm, then 300 mm / 150 mm/lift = 2 lifts are needed. The pipe invert depth simplifies to the re
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: A granular pipe bedding material needs to be compacted to 95% Standard Proctor Density. The specified lift thickness for this material is 150 mm. If the pipe invert is 2 metres below existing grade, and 300 mm of bedding is required below the pipe, how many lifts of bedding material are needed?
Answer options: ✅ 2 lifts
- 3 lifts
- 1 lift
- 4 lifts
Correct answer: 2 lifts
Explanation: If 300 mm of bedding is required below pipe, and each lift is 150 mm, then 300 mm / 150 mm/lift = 2 lifts are needed. The pipe invert depth simplifies to the required bedding depth.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.