A trench is being excavated in soil requiring a 1:1 (horizontal to vertical) slope for stability. If the trench is 4.0 metres deep, and the bottom width is 1.0 metre, what will be the approximate top width of the trench?
For a 1:1 slope, the horizontal distance added to each side is equal to the depth. So, for each side, 4.0 metres horizontal (depth) must be added. Total top wid
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: A trench is being excavated in soil requiring a 1:1 (horizontal to vertical) slope for stability. If the trench is 4.0 metres deep, and the bottom width is 1.0 metre, what will be the approximate top width of the trench?
Answer options:
- 9.0 metres ✅ 5.0 metres
- 7.0 metres
- 8.0 metres
Correct answer: 5.0 metres
Explanation: For a 1:1 slope, the horizontal distance added to each side is equal to the depth. So, for each side, 4.0 metres horizontal (depth) must be added. Total top width is 1.0 m (bottom) + 4.0 m (left side) + 4.0 m (right side) = 9.0 metres. My apologies, I calculated it wrong the first time! The correct answer involves adding the slope twice.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.