Your excavator's manufacturer specifies a track sag of 150 mm when measured between the idler and the front carrier roller. You measure a sag of 200 mm. What does this indicate and what action should be taken?
A sag of 200 mm when 150 mm is specified indicates the track is too loose. To correct this, grease should be added to the track tensioning cylinder to increase
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
Question: Your excavator's manufacturer specifies a track sag of 150 mm when measured between the idler and the front carrier roller. You measure a sag of 200 mm. What does this indicate and what action should be taken?
Answer options:
- The track tension is too tight; release some grease from the tensioning cylinder. ✅ The track tension is too loose; add grease to the tensioning cylinder.
- The track tension is optimal for soft ground conditions; no action required.
- The track requires replacement as it has stretched beyond repair.
Correct answer: The track tension is too loose; add grease to the tensioning cylinder.
Explanation: A sag of 200 mm when 150 mm is specified indicates the track is too loose. To correct this, grease should be added to the track tensioning cylinder to increase tension. This ensures proper track engagement and prevents de-tracking, aligning with manufacturer specifications.
Start free practice for Excavator Operator Certification Exam Prep
263 questions · no signup required · 40 free questions per day
More about Excavator Operator Certification Exam Prep
Related Questions
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
- According to IUOE best practices, what is the LAST thing an operator should do before leaving the excavator's
- Travel on slope — bucket should be:
More for Excavator Operator Certification Exam Prep candidates
Question explanations
- During a final inspection of an excavator, prior to beginning work, an operator notices significant play in th
- An excavator operator is preparing to dig a trench in cohesive soil. To achieve maximum breakout force, what a
- Which control typically governs the arm (or dipper arm) movement for an excavator?
- What condition might require sloping or shoring of a trench less than 1.2 meters (4 feet) deep?
Ready to practice?
Free, no signup required. Build a wrong-question list as you go.
Start Free Excavator Operator Certification Exam Prep Practice →Related courses
Other Canadian certifications candidates often prepare for alongside this one.