A trench is being excavated in cohesive soil to a depth of 2.1 m. What is the minimum slope angle for the sides of the trench, without additional shoring or support, as per Canadian occupational health and safety regulations?

For trenches in cohesive soil up to 3.6 m deep, Canadian OHS regulations typically allow a maximum slope of 1 horizontal to 1 vertical (45 degrees) without addi

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

Question: A trench is being excavated in cohesive soil to a depth of 2.1 m. What is the minimum slope angle for the sides of the trench, without additional shoring or support, as per Canadian occupational health and safety regulations?

Answer options: ✅ 1:1 (45 degrees)

  • 3:4 (approximately 37 degrees)
  • 1:2 (approximately 26.6 degrees)
  • 1:3 (approximately 18.4 degrees)

Correct answer: 1:1 (45 degrees)

Explanation: For trenches in cohesive soil up to 3.6 m deep, Canadian OHS regulations typically allow a maximum slope of 1 horizontal to 1 vertical (45 degrees) without additional shoring. Slopes shallower than this, like 1:2 or 1:3, are for less stable soil types or greater depths.

Start free practice for Excavator Operator Certification Exam Prep

263 questions · no signup required · 40 free questions per day

Start Practice →

More about Excavator Operator Certification Exam Prep

Related Questions

More for Excavator Operator Certification Exam Prep candidates

Ready to practice?

Free, no signup required. Build a wrong-question list as you go.

Start Free Excavator Operator Certification Exam Prep Practice →

Related courses

Other Canadian certifications candidates often prepare for alongside this one.